Falsework for the I-210 Gold Line Bridge should be completely up next week.

After Foothill Extension Construction Authority representatives met with Congressional officials and staff last week for an update on the Foothill Extension project, Chief Executive Officer of the project, Habib F. Balian announced that the falsework--the temporary framework that provides structural support--for the I-210 Gold Line Bridge is almost complete.  Skanska predicts the falsework will be fully up early next week. 

Balian describes the progress as “a significant milestone for the project that required more than 20 full late-night closures of the eastbound I-210 Freeway over the last two months.”

Once the falsework is finished, crews will move on to building the main cross beam and superstructure.

Find out what's happening in Monroviawith free, real-time updates from Patch.

We’ve removed the ability to reply as we work to make improvements. Learn more here

The views expressed in this post are the author's own. Want to post on Patch?

More from Monrovia